Foamed Bitumen Stabilisation Project – Warwick, Qld
by Warren Smith, Stabilised Pavements of
Australia
Introduction
The Department of Main Roads, Queensland, has for some time been looking
at using bitumen in stabilisation works to overcome some of their problems.
They have been using cements in their stabilisation to rehabilitate
pavements successfully for many years and they have just recently
successfully recommenced the use of lime in subgrades.
Due to the fact that many of their highways in Queensland have thin
pavement depths over very plastic subgrades, the use of deep lift
cementitious pavement rehabilitation has been more limited than in other
States.
In the early nineties, the QDMR carried out a
number of trial projects using combinations of bitumen emulsions and cement
with only moderate results. However, with the reappearance of foamed bitumen
stabilisation with a higher level of technology in both the understanding of
the procedures and the machinery used, the QDMR has begun to undertake a
number of foamed bitumen stabilisation projects.
To view the full report of this project ( PDF
format 197KB) Click here.
You will need Adobe® Acrobat® Reader™ to view the PDF file.
To download a free copy of Acrobat click on the logo to the right.
Postscript
(June 1999)
As a postscript, this job was successfully completed in late May, 1999.
It was actually extended to be 18km or approximately 143,500m² of State
Highway completely rehabilitated using foamed bitumen stabilisation in 37
working days under traffic.
The work
methodology was refined slightly during the job to obtain the best results
most efficiently. The total cost to the Department of Main Roads, including
the bitumen seal wearing course, was between $16.50 and $18.00/m².
By enhancing the existing road pavement asset insitu using Foamed Bitumen
Stabilisation, the Main Roads has been able to avoid the removal and dumping
of up to 60,000 tonnes of "unsuitable" material and the quarrying and
introduction of up to 60,000 tonnes of new pavement material.
Hence, in
terms of engineering excellence, huge savings in costs, the speed and lack
of disruption, and the environmental benefits of recycling the deteriorated
asset, this project has been an unqualified success.